    Laying Paving Stones

    The Complete How To Guide to Laying Paving Stones

    Do you want a more interesting and durable approachway to your property? Concrete pavers are a practical way to lay hard-wearing paths, patios, courtyards and driveways, without just pouring plain concrete. Pavers can be laid in stages, and even better, they can be lifted if drains, cables or pipes underneath ever need servicing.

    Let’s Make a Plan

    Do a scale drawing of the area you want to pave. From that, estimate the quantities you need. Remember, some extra materials will be required for cutting, depending on the size and shape of the area you’re paving.

    Materials

    Buy all your pavers from one place and from the same batch if possible, to avoid differences in colour that can result from different batches. If you can’t buy all in one batch, mix the pavers up before laying. Please note: pavers may also displa a “whitening” otherwise known as efflorescence effect. This is a characteristic of many masonry products and does diminish over time. If you have any trouble working out the quantities of each paver you need, PlaceMakers offers a free estimation service.

    Like any building job, you’ve got to get the foundations right. Extensive areas of paving, particularly where large areas of soft topsoil have to be dug out, require large volumes of materials. There are four main materials:

    • Pavers
    • Bedding sand
    • Base course material (usually)
    • Joint sand.

    Laying paving stones illustration

    Ordering and Sorting Materials

    On smaller sites, piles of materials can crowd the area you want to pave. If that’s the case, take delivery of the later stage materials only as you are ready to use them. That means digging out and laying the base course material first, then get the bedding sand and pavers delivered.

    Tools you'll need

    • Tape measure
    • Pencil
    • Stringlines
    • Spirit level
    • Spade
    • Shovel
    • Rake
    • Broom
    • Screed board
    • Plate compactor(hired)
    • Concrete saw/Paver splitter/Bolster (hired)
    • Weed matting (optional)

    Choosing the Right Paver

    Criteria

    Weight of traffic
    Some pavers can only withstand pedestrian use. Others will take light vehicle traffic. Even stronger pavers will handle heavy vehicles. Check the specifications with PlaceMakers.

    Paver shape and size
    Your choice should suit the size and shape of the area being paved. Laying pattern: Again, this should suit the area being paved. Laying options include: 45 degree herringbone, stretcherbond, basketweave, soldier courses along the edges

    Check the manufacturer’s recommendations.

    Paving stone patterns - illustration

    Dry Cast Paving

    1. Digging Out

    A. Determine the finished level of the highest part of your paving. Against buildings, that should be at least 150mm below the level of concrete floors,  or below the ground level under timber floors. From there, your paving should slope between 15mm to 30mm per metre away from the building. This prevents puddling or running under buildings.

    B. Dig out the area to be paved to the combined depth of the three layers, i.e. pavers depth plus bedding sand and base course depths.

    • Paver thickness is set by the expected weight of traffic.
    • Bedding sand is to be laid loose but compacted to achieve a depth of 30mm.
    • Base course is the only variable. It is the foundation of your paving. The thickness of the base course depends on the firmness of the underlying ground, or “sub-grade”. Soft sub-grade has to be dug out deeper because it needs a thicker base course than hard sub-grade. To test the sub-grade, dig down to about 200mm in several places within the planned paved area, then test the hardness of the sub-grade by walking on and stamping your heel into it. Refer to tables over-page.

    2. Preparing the Sub-grade

    Even after excavating, the sub-grade might have holes that need filling to bring it up to the desired level. Fill these with base material, and compact in layers no more than 100mm thick using a plate compactor or a rammer for small areas. Thorough compaction is vital especially at edges. The finished sub-grade level should be within 20mm of the contour of the finished paving.

    3. Preparing the Base Course

    This should also be laid in layers no thicker than 100mm and compacted to a uniform dense condition, especially around manholes and kerbs. The finished texture of the base course should not allow bedding sand to filter through. The final surface of the base course should match the contour of your finished paving with no bumps, and no holes deeper than 10mm.

    4. Placing the Edging

    Edging is important to prevent sideways movement of pavers, and to stop bedding sand leaking out.

    Edging options

    • Soldier Course of either standing or fl at pavers (see below)
    • Paving Kerb – segmented raised kerbing
    • Paving Edge – concealed, underground PVC strip
    • Haunching – concealed concrete strip (see below)

    Soldier Course Illustration

    Haunching Illustration

    5. Preparing the Bedding Sand Base

    Bedding sand supports your pavers, but will not hide irregularities in the base course. It should be coarse river sand (not beach sand), and damp but not wet.

    1. Don’t compact bedding sand directly. It compacts under the pavers. To test how much the thickness will reduce, spread some sand over a small area. Lay a paver on top and thump that with a rubber hammer. The resulting reduction in sand thickness will tell you how much your sand compacts.
    2. Pave in manageable sized areas. Spread sand only over an area you know you can finish in one session and get to without walking on. Spread the sand to slightly more than the depth your rubber hammer test indicated would produce a compacted sand depth of between 20mm and 30mm. You will usually need to start with the un-compacted sand bed between 5mm and 10mm thicker than its compacted depth.
    3. Screed the sand to a uniform level. As with any screeding, you need temporary guides or runners at each side to run your screed board on.

    If you have already laid a Soldier or Kerb course, you may be able to use that to support your runners. If the area to be paved is too wide you’ll need to drive pegs, and fix your runners to them, just like concrete boxing (see below).

    Screed on runners illustration

    Detail illustration - not to scale - of screed on runners paving

    6. Laying the Pavers

    1. Start from the straightest convenient edge, and lay your pavers with a space of 2mm to 4mm between them. Some pavers have spacer nibs which achieve that automatically. The space allows joint sand to penetrate around the pavers. Always start at the bottom of sloped areas.
    2. Lay all full pavers first: then cut and lay any pieces. Cut pavers with a  diamond concrete saw, paver splitter (both available from hire centres) or, for  small areas, a bolster.
    3. Don’t run vehicles over the paving until it’s completely finished. To get a loaded wheelbarrow across, lay heavy planks down as running boards.

    7. Compacting the Pavers

    Your pavers now need to be consistently compacted over the whole area. Include a minimum of three passes with compactor each at 90 degrees to each other.

    1. For a small area, use a rubber hammer on a short length of heavy timber: say a piece of 150 x 50mm. For most other jobs, use a plate compactor.
    2. When the pavers are all compacted, sweep joint sand over the whole area and compact again. The compactor will drive the sand into the joints. Keep sweeping and compacting until all joints are filled.
    3. Joint sand should be fine dry plaster sand with angular particles that lock well together. It is also sold as paving sand and some types incorporate a weed preventative.
    SUB-GRADE TESTING
    Sub-grade Strength Weak Moderate Strong
    Walking and heel test footprints Walking leaves distinct footprints Heel leaves an impression Neither walking or heels leaves an impression
    Driveways (light vehicle traffic only) 175mm base material 125mm base material 75mm base material
    Pedestrian use only 75mm base material 50mm base material No base material required, just sand
    EXCAVATION EXAMPLE
    Paver thickness (driveway) 60mm
    Bedding sand (compacted) 30mm
    Base Course (moderate sub-grade firmness) 125mm
    = TOTAL EXCAVATION DEPTH
    (below fi nished paving level) 215mm
    BASE COURSE MATERIAL
    • Should be crushed rock including particles of all sizes.
    • No particles should have a diameter more than one third of the thickness of the required base course layer.
    • It should contain no soil or plant material.
    • Lay geotextile fabric first where soft clay, which might push into and through the base course material.
    • For layers of 100mm thick or more, use 40mm all in aggregate.

    Maintenance

    In most cases maintenance will be minimal. If some pavers settle unevenly, or if underground services need to be exposed, your paving may require re-laying. To do this simply follow the procedures given above. It would pay to add a layer of weed matting below the sand layer to stop any weeds that could grow up and between your pavers. Where paving is cleaned or has water running across it the joint sand may require topping up periodically. To enhance the appearance of your paving special sealers are available. These may require reapplication over time. Ask at your PlaceMakers Firth Centre.

    NOTE: Building or landscaping work may have to comply with the New Zealand Building Code and your local Council requirements. Talk to the building inspectors at your council. They can provide helpful details of such matters and say whether or not a permit is required for the work you wish to do.

    Wet Cast Paving

    Choose your site carefully

    Take note of potential problems such as drains, trees and electrical wiring.

    Check the height of the surface to be paved, take measurements and draw plans. Set the paving below the fl oor level and slightly sloped away from the house, or areas that you would want to keep water away from.

    Choose your pavers and design, measure up and order.

    If the ground is firm and well compacted excavate to a depth of 75mm, then move to next step. If soft or a fi lled site, excavate 75-100mm deeper and add 75-100mm of top course and compact well with a plate compactor.

    Now set up string-lines to give you lines to follow for both height and gapping.

    Now you can choose one of two laying methods:

    1. Spread and level a fi ne loose bedding sand, dampen and lightly compact. Then screed level and choose your laying pattern. This method is quick, easy and if the levelling is done well, gives a great fi nish.
    2. Prepare a mix of sand and cement with water to put on the base. Roughly level and then tap your pavers down into it. Remember, where they sit they stay. This method requires more work, as precision laying is far less forgiving. Once the sand and cement mix hardens, your pavers can’t be easily lifted or moved.

    NB:It is critical to allow a minimum gap of 8mm between pavers, although a 10mm to 15mm gap is recommended.

    This gap allows you to have some fl exibility if there are any minor height discrepancies and also removes the effect of any slight size variations that may occur in hand made pavers.

    Some pavers may need cutting. You can hire a suitable saw from hire centres or use an angle grinder with a masonry blade. Always read and familiarise yourself with the operating instructions of any machinery used and take all safety precautions.

    Do not use compaction equipment over pavers.

    Hose off pavers, let them dry, then use either pave joint sand, mortar pointing, or pavelock grouting sand. It is important to follow the product directions. If compaction is required, go over pavers with a rubber mallet.

    Use dry sand and cement mix to trowel an edge from the top of the paver, away at a 45 degree angle to give the pavers a border, or haunch, to hold them in place.

    Please Note: Whilst the advice and recommendations contained in this article have been produced with proper care, they are offered only with the objective of assisting those interested in home improvement projects and PlaceMakers does not accept responsibility for the advice, recommendations, etc. contained herein.

    Explore the PlaceMakers paving range

    There's something for every home with our wide range of pavers and decorative stones.  

    Explore now:

    Concrete Paving

    The natural look of concrete pavers creates a solid, earthy feeling - while the different sizes, shapes, and colours allow you to get creative with patterns.  

    Explore Concrete Paving

    Natural Paving

    Our natural stone pavers are made from the world's abundant resources of porcelain, sandstone, and granite. These timeless pavers bring character to any home. 

    Explore Natural Paving

    Decorative Stones

    From classic river pebbles to crushed chips and sparkling alpine crystal, we have a range of decorative stone covers to complete your landscaping look. 

    Explore Decorative Stone

    Permeable Paving

    Permeable pavers come in a variety of shapes and textures and help to manage stormwater flows, reduce runoff, and filter pollutants from the water. 

    Explore Permeable Paving

    Get Inspired

    PlaceMakers can help you get started on a paving project to suit your space, get inspired below and then come in store to discuss your next project.

    Cottage Garden

    Learn how the owners of a 1940’s cottage garden in Waiake, Torbay, transformed their wrap-around coastal garden into a low maintenance retreat.

    View Project

    Planter Box Project

    Learn how Dean McGowan, a DIY enthusiast and PlaceMakers team member, recently built this solid and multi-tasking planter box.

    View Project

    Vulcan Deck Lake Tarawera

    Vulcan Decking was selected as a local sustainable timber decking option because it is hardwearing and endures the test of time.

    View Project

    Decking Guides

    View our helpful tips on decking installation through to our decking screw selection guide.

    We are here to help you every step of the way to accomplish your decking project.